Water & Waste Water

Lake Canobolas Water and Sewer Main, Orange, NSW

The purpose of the new water and sewer main is to remove the need of existing services and connect onto the existing Orange networks. The water main is a “renewal” project that will provide eligible residents and users of the lake, scout camp and other facilities with potable water of a higher quality. The existing water main is a 300mm Cast Iron main that is over 100 years old and is oversized to meet the needs of the Lake Canobolas area. Through the implementation of a sewer pumping station and rising main, the existing septic systems that are currently utilised will be removed from the catchment of the Lake Canobolas Reserve and Molong Creek and be pumped into the Orange sewer network, being treated further downstream at the Orange Waste Water Treatment Plant. The proposed route for the pipeline runs between Towac Park (south west of Orange) to Lake Canobolas across a variety of landscapes, ranging from the fringes of the urban residential area, to small rural holdings, horse stud/agistment properties, to larger orchards and mixed agricultural land, and then the ‘environmental management’ areas of the Lake Canobolas broader Reserve in the west.

CONTRACT TYPE: AS4000-1997

WORK TYPE: Construction Only

LOCATION: Nashdale Orange, NSW 2800

CLIENT: Orange Council

Urraween Pump Station-Harvey Bay-Fraser Coast, QLD

Construction of a new booster pump station building housing the following:
  • Pump room containing reservoir bypass pipework for gravity flow, boosted pump flow and a spare space for a future pump
  • Switch room for the housing of the new site wide switchboards and pump drives
  • Chemical storage room housing the new site wide sodium hypochlorite storage, analysing and dosing facility
  • Chemical delivery truck bunded area
  • Booster pump installation (principal free issue)
  • New pump station pipework including critical cut-ins
  • New below ground conduit system for new site wide electrical/control systems
  • New site wide storm water collection and discharge system
  • New site wide dosing and sampling pipework outside of chemical storage room
  • New access road and associated landscaping

CONTRACT TYPE: AS4000

WORK TYPE: Construction

LOCATION: Harvey Bay, Fraser Coast

CLIENT: Fraser Coast Regional Council

DURATION: 15 Months

Bloomsbury Water Main, Mackay QLD

This project is to maintain supply of water to Bloomsbury residents by adding a new pipeline, new storage tank and a new booster pump. The new pipeline provides opportunity for residents along the pipeline to connect to the main and be provided with safe treated water from a plentiful supply. It includes:
  • 15.3km of Watermains:
  • Size varies from 40mm to 150mm,
  • Material to be PE, PVC and DICL
  • Booster pump station
  • Pumpstation Building Incl Switchroom
  • Reservoir Tank
  • Access Track

CONTRACT TYPE: AS 2124-1992

WORK TYPE: Design and Construction

LOCATION: Bloomsbury, Mackay QLD

CLIENT: Mackay Regional Council

DURATION: 15 months

Huskisson Sewer Pump Station, Gravity and Rising Main

Carrying out of minor design and construction works for HUSKISSON SEWER PUMP STATION (SPS) 7,  Building, Switchroom, Wet well (5m dia x 7m deep), DN450PE of GRAVITY MAIN &RISING MAIN UPGRADES.

CONTRACT TYPE: AS 4000-1997

WORK TYPE: Design and Construction

LOCATION: Huskission, Nowra

CLIENT: Shoalhaven City Council

DURATION: 9 months

Bargara WWTP to Rubyanna-QLD-Rising Main-7km of 450 GRP

Connecting Sewer Rising Main from Bargara WWTP to Rubyanna WWTP.

CONTRACT TYPE: AS2124

WORK TYPE: Sewer Rising Main

LOCATION: Bundaberg, QLD

CLIENT: Bundaberg Regional Council

DURATION: 12 months

Illaroo Road Pump Station and Stage 2 Water Mains

Separable Portion (SP) A: Illaroo Road Water Pump Station  Separable Portions (SP) B: Illaroo Road Stage 2 Water Pipelines – Approx. 8.3km 450 PE 

CONTRACT TYPE: AS 4000-1997

WORK TYPE: Pumpstation and Water Mains Construction

LOCATION: Nowra

CLIENT: Shoalhaven Council - Shoalhaven Water

DURATION: 16 months

Scott St – Subdivision

This project includes Clearing, Cut and Fill, Earthworks, Stormwater drainage pipes and pit, Kerbs and Gutter, Water supply, Sewer reticulation, Pavements for new road construction, Pavements widening existing road carriageway, Concreting works, Landscape, Power and NBN and associated activities.

CONTRACT TYPE: AS4000

WORK TYPE: Complete Subdivision Development x 25 Lots

LOCATION: Condobolin

CLIENT: Lachlan Shire Council

DURATION: 12 Months

Muswellbrook Water Main Renewal

Upgrade several streets watermain reticulation network.

CONTRACT TYPE: AS4000

WORK TYPE: Water Main Reticulation

LOCATION: Muswellbrook

CLIENT: Muswellbrook Council

DURATION: 6 months

Greater Hume-Smoke Testing

CONTRACT TYPE: General Council

WORK TYPE: Smoke Testing the Sewer Reticulation Line

LOCATION: Greater Hume

CLIENT: Greater Hume Council

DURATION: 3 months

Portland Trunk Main and Reticulation System

The Lithgow Local Government Area (LGA) is a relatively large geographical area of 4,551 square kilometres, located approximately 140 kilometres west of the Sydney CBD and within the eastern part of the Central West Region. The Lithgow LGA lies almost wholly within the Wiradjuri Aboriginal nation, with the Gundungurra nation situated to the south and the Darug nation to the east.   This project involved the water mains construction throughout the Portland village including the new trunk construction of a new main to service the Foundations site and renewal of mains in the east Portland area.

CONTRACT TYPE: AS 4000 - 1997

WORK TYPE: D&C

LOCATION: Portland NSW

CLIENT: Lithgow Council

DURATION: 6 months

Tweed Head – Sewer Rising Main Construction ~2.2km

  • Work as a PRINCIPAL CONTRACTOR
  • Supply and installation of DN375 Sewer Rising Main approx. 2.2km
  • Supply and installation of Scour valves with Pits
  • Supply and installation of Air valves with Pits
  • Supply and installation of Barometric Pit with the Flowmeter
  • Work adjacent/on to the roads
  • Reseal the road

CONTRACT TYPE: MW21

WORK TYPE: Construction 2.3km of DN375 GRP

LOCATION: Tweed Head

CLIENT: Tweed Shire Council

DURATION: 6 months

Dubbo – Water Main Replacement

  • All works related to the Installation of DN150 (PVC-O) Water Main Pipeline and associated Fittings
  • All works related to the Installation of DN250 (DI) Water Main Pipeline and associated Fittings
  • All works related to the Installation of DN250 (PVC-O) Water Main Pipeline and associated Fittings
  • All works related to the Installation PRV Pit and fitting configuration
  • Testing, flushing and disinfecting of water mains 

CONTRACT TYPE: AS 4000 - 1997

WORK TYPE: Construction Only

LOCATION: Dubbo

CLIENT: Dubbo Regional Council

DURATION: 6 months

Cumnock Town – Water Main Pipe Cleaning

It involves cleaning and disinfecting the water main for the entire town.

CONTRACT TYPE: AS 4000 - 1997

WORK TYPE: Water Pipeline Cleaning - Whole Town

LOCATION: Cumnock NSW 2867

CLIENT: Cabonne Council

DURATION: 6 months

Water Main Cleaning and Disinfection- 80km pipeline

80 km pipeline cleaning. It includes pigging/swabbing, flushing and disinfection of 80km pipeline in Molong, Cumnock and Yeoval  towsnship.

CONTRACT TYPE: AS 4000 - 1997

WORK TYPE: Cleaning and Disinfection

LOCATION: Molong-Yeoval

CLIENT: Cabonne Council

DURATION: 6 months

VIC – Wodonga -Water Main Relocation

CONTRACT TYPE: AS 4000

WORK TYPE: D&C

LOCATION: Wodonga Water Main Relocation - VIC

CLIENT: North East Water

NSW-Albury Water Main Replacement

It includes replacing of the 3 sections of water mains including underboring, trenching, installing PVC-M pipeline, hydrants, STOP Valves and commissioning (pressure test).

CONTRACT TYPE: MW21- Contract

WORK TYPE: Water Main Replacement

LOCATION: NSW Albury

CLIENT: Albury Council

DURATION: 3 months

Crookwell Water Main – NSW

Crookwell potable, Carrington Street Crookwell, is approximately 300metres, 100mm Blue Brute class 16. This project includes 7 right hand close stop valves, 6 hydrants and 2 x 100mm tees, all metal is to have protective coatings. There is 14 X 20mm domestic water connection (any galvanized pipes to be replace by copper), and 3 services require 32mm underboring of the road. Note: This is an RMS road.

CONTRACT TYPE: AS 4000

WORK TYPE: D&C

LOCATION: Carrington Street, Crookwell NSW

CLIENT: Carrington Street, Crookwell NSW

Crookwell Sewer Main – NSW

It involved supply and installation of approx 1.0 km of sewer main installation using DN150 oPVC pipe. It includes number of underboring and creek crossing using DN150 PE and 15 sewer manholes (1050).

CONTRACT TYPE: AS 4000

WORK TYPE: D&C

LOCATION: Saleyards Road, Crookwell NSW

CLIENT: Upper Lachlan Council

Hilltop Water Main Replacement – NSW

Hilltops Council (Council) is a local government area (LGA) in the South West Slopes region of New South Wales, Australia. This LGA was established on 12 May 2016 through the amalgamation of the former council areas of Boorowa, Harden and Young. The LGA covers approximately 7,139Km2 with an estimated population of 18,994 (2016).

CONTRACT TYPE: Principal Contractor (AS 4000)

WORK TYPE: D&C

LOCATION: Milvale Road, Young

CLIENT: Hilltop Council

DURATION: 2021

Gunning Sewer Main – NSW

It involved supply and installation of approx 200m of sewer main installation using DN150 oPVC pipe. It includes 4 x underboring as a sleeving and installation of 4 x sewer manholes (1050) and connecting to the lagoon. Property connection of DN65 PE

CONTRACT TYPE: AS 4000

WORK TYPE: D&C

LOCATION: Biala Road, Gunning

CLIENT: Upper Lachlan Council