Water Main Cleaning and Disinfection- 80km pipeline

CONTRACT TYPE: AS 4000 - 1997

WORK TYPE: Cleaning and Disinfection

LOCATION: Molong-Yeoval

CLIENT: Cabonne Council

DURATION: 6 months

ABOUT PROJECT:
80 km pipeline cleaning. It includes pigging/swabbing, flushing and disinfection of 80km pipeline in Molong, Cumnock and Yeoval  towsnship.
SOW:
Molong to Yeoval water main swabbing, flushing and disinfection
  • Swabbing of water supply main from Molong to Yeoval
  • Flushing of water supply main from Molong to Yeoval
  • Disinfection of water supply main from Molong to Yeoval
  • Flushing of Cumnock Reservoir
  • Flushing of Yeoval Reservoir
  • Disinfection of Cumnock Reservoir
  • Disinfection of Yeoval Reservoir
  • Sampling and analysis of water supply mains and reservoirs
Yeoval township water main swabbing, flushing and disinfection
  • Swabbing of existing non potable water mains in Yeoval township
  • Flushing of existing non potable water mains in Yeoval township
  • Disinfection of existing non potable water mains in Yeoval township
  • Sampling and analysis of water supply mains
INNOVATION:
Usiing Ozone system for reticulation cleaning