CONTRACT TYPE: AS4000
WORK TYPE: Complete Subdivision Development x 25 Lots
LOCATION: Condobolin
CLIENT: Lachlan Shire Council
DURATION: 12 Months
ABOUT PROJECT:
This project includes Clearing, Cut and Fill, Earthworks, Stormwater drainage pipes and pit, Kerbs and Gutter, Water supply, Sewer reticulation, Pavements for new road construction, Pavements widening existing road carriageway, Concreting works, Landscape, Power and NBN and associated activities.
This project includes Clearing, Cut and Fill, Earthworks, Stormwater drainage pipes and pit, Kerbs and Gutter, Water supply, Sewer reticulation, Pavements for new road construction, Pavements widening existing road carriageway, Concreting works, Landscape, Power and NBN and associated activities.
SOW:
Road:
Road:
- 1287m of kerb and gutters
- 833 sq.m of base
- 90 cu.m of bitumen
- 1287m of subsoil drain
- 31m of DN150 uPVC
- 122m of DN225 uPVC
- 55m of DN300 uPVC
- 416m of DN375 FRC RRJ
- 153m of DN450 FRC RRJ
- 153m of DN525 FRC RRJ
- 48m of DN600 FRC RRJ
- 11m of DN675 RRJ
- 274m of DN900 RRJ
- 28 x pits
- DN100 uPVC, with 136m pre curved
- 11 x SV. 9 x Hyd, 3 x Connection to existing
- 22 x property connections
- DN150 SN8
- 12 x DN150 Junctions
- 5 x DN150 Junction off dead end
- 8 x DN150 Junction off maintenance holes
- 13 x Manholes
- Over 2km of 125 and 140 uPVC conduit
- New Substations
- Mini pillar
- Link Pillar
- Install new Transformers
- Connection to Essential Energy
- Level-3 Design
- P100 conduit
- P8 Pit
- P5 Pit
- Cabling
- Fibre
- Property Connection with 20mm
CHALLENGE:
- Multiple utilities at the same time
- building share trench design and its execution
- dealing the with various regulatory authorities
- dealing the with various asset owner
OUTCOME:
Successful
Successful
INNOVATION:
Project Management with innovative ideas
Project Management with innovative ideas