Scott St – Subdivision

CONTRACT TYPE: AS4000

WORK TYPE: Complete Subdivision Development x 25 Lots

LOCATION: Condobolin

CLIENT: Lachlan Shire Council

DURATION: 12 Months

ABOUT PROJECT:
This project includes Clearing, Cut and Fill, Earthworks, Stormwater drainage pipes and pit, Kerbs and Gutter, Water supply, Sewer reticulation, Pavements for new road construction, Pavements widening existing road carriageway, Concreting works, Landscape, Power and NBN and associated activities.
SOW:
Road:
  • 1287m of kerb and gutters
  • 833 sq.m of base
  • 90 cu.m of bitumen
Drainage-2550m:
  • 1287m of subsoil drain
  • 31m of DN150 uPVC
  • 122m of DN225 uPVC
  • 55m of DN300 uPVC
  • 416m of DN375 FRC RRJ
  • 153m of DN450 FRC RRJ
  • 153m of DN525 FRC RRJ
  • 48m of DN600 FRC RRJ
  • 11m of DN675 RRJ
  • 274m of DN900 RRJ
  • 28 x pits
Water-2636m:
  • DN100 uPVC, with 136m pre curved
  • 11 x SV. 9 x Hyd, 3 x Connection to existing
  • 22 x property connections
Gravity Sewer-2774m:
  • DN150 SN8
  • 12 x DN150 Junctions
  • 5 x DN150 Junction off dead end
  • 8 x DN150 Junction off maintenance holes
  • 13 x Manholes
Power
  • Over 2km of 125 and 140 uPVC conduit
  • New Substations
  • Mini pillar
  • Link Pillar
  • Install new Transformers
  • Connection to Essential Energy
  • Level-3 Design
NBN-2500m
  • P100 conduit
  • P8 Pit
  • P5 Pit
  • Cabling
  • Fibre
  • Property Connection with 20mm
CHALLENGE:
  • Multiple utilities at the same time
  • building share trench design and its execution
  • dealing the with various regulatory authorities
  • dealing the with various asset owner
OUTCOME:
Successful
INNOVATION:
Project Management with innovative ideas